Total estimation of the materials’ quantities
ESTIMATION OF CONCRETE (m³)
Level |
Superstructure |
Foundation |
Sum (m3) |
|
Slabs - Beams |
Columns |
Footings |
|
Ground floor |
4.97 |
1.60 |
|
6.6 |
Basement |
5.41 |
3.85 |
5.51 |
14.8 |
Sum (m3) |
10.38 |
5.45 |
5.51 |
21.3 |
ESTIMATION OF FORMWORK (m²)
Level |
Superstructure |
Foundation |
Sum (m2) |
|
Slabs - Beams |
Columns |
Footings |
|
Ground floor |
31.78 |
16.00 |
|
47.8 |
Basement |
35.24 |
32.75 |
21.72 |
89.8 |
Sum (m2) |
67.02 |
48.75 |
21.72 |
137.6 |
ΠΡΟΜΕΤΡΗΣΗ ΟΠΛΙΣΜΟΥ (m)(kgr)
|
|
Superstructure |
Foundation |
Sum |
|
Rebars |
Slabs |
Beams |
Columns |
Slabs |
Footings |
Beams |
(m) |
(Kgr) |
|
|
Ø8 |
129.98 |
- |
- |
- |
- |
- |
329.42 |
129.98 |
|
Ø10 |
132.08 |
- |
187.11 |
- |
- |
- |
517.72 |
319.19 |
|
Ø12 |
- |
- |
- |
- |
76.17 |
61.14 |
154.65 |
137.30 |
|
Ø14 |
- |
192.65 |
- |
- |
- |
- |
159.22 |
192.65 |
|
Ø16 |
- |
- |
395.05 |
- |
- |
197.17 |
374.83 |
592.23 |
|
Sum of rebars |
262.07 |
192.65 |
582.16 |
- |
76.17 |
258.31 |
1535.83 |
1371.36 |
|
Stirrups
|
Slabs |
Beams |
Columns |
Slabs |
Footings |
Beams |
(m) |
(Kgr) |
|
|
Ø8 |
- |
92.89 |
309.72 |
- |
- |
- |
1020.34 |
402.61 |
|
Ø10 |
- |
- |
- |
- |
- |
86.32 |
140.00 |
86.32 |
|
Sum of stirrups
|
- |
92.89 |
309.72 |
- |
- |
86.32 |
1160.34 |
488.92 |
|
SUM |
262.07 |
285.54 |
891.88 |
- |
76.17 |
344.63 |
2696.17 |
1860.28 |
|